Summary of Work

  • Staged traffic control and phased construction
  • Environmental protection measures and site isolation
  • De-watering, cofferdam, and temporary flow passage
  • Removal of existing bridge components
  • Earth excavation for the structure
  • Type C concrete removals and repairs
  • Laminated elastomeric bearing replacements
  • Concrete in ballast wall, wing wall, and bridge seats
  • Bridge jacking and temporary structure supports
  • Replacement of the steel floor beams, chords, lateral x-bracing, and bearing connections